  • Course Schedule II 解答

    Question

    There are a total of n courses you have to take, labeled from 0 to n - 1.

    Some courses may have prerequisites, for example to take course 0 you have to first take course 1, which is expressed as a pair: [0,1]

    Given the total number of courses and a list of prerequisite pairs, return the ordering of courses you should take to finish all courses.

    There may be multiple correct orders, you just need to return one of them. If it is impossible to finish all courses, return an empty array.

    For example:

    2, [[1,0]]

    There are a total of 2 courses to take. To take course 1 you should have finished course 0. So the correct course order is [0,1]

    4, [[1,0],[2,0],[3,1],[3,2]]

    There are a total of 4 courses to take. To take course 3 you should have finished both courses 1 and 2. Both courses 1 and 2 should be taken after you finished course 0. So one correct course order is [0,1,2,3]. Another correct ordering is[0,2,1,3].

    Solution

    Similar with "Course Schedule", the only difference is that we need to record path.

    Note: an empty array is the array with length = 0.

     1 public class Solution {
     2     public int[] findOrder(int numCourses, int[][] prerequisites) {
     3         // This problem is to print one possible topological sort result
     4         // First, we need to construct a directed graph in the form of adjacency list
     5         List<Integer>[] adjacencyList = new ArrayList[numCourses]; 
     6         int[] result = new int[numCourses];
     7         int[] degree = new int[numCourses];
     8         Arrays.fill(degree, 0);
     9         for (int j = 0; j < numCourses; j++) {
    10             List<Integer> tmpList = new ArrayList<Integer>();
    11             tmpList.add(j);
    12             adjacencyList[j] = tmpList;
    13         }
    14         int length = prerequisites.length;
    15         for (int j = 0; j < length; j++) {
    16             int[] pair = prerequisites[j];
    17             adjacencyList[pair[1]].add(pair[0]);
    18             degree[pair[0]]++;
    19         }
    20         
    21         // queue is to store nodes with 0 in-degree
    22         Queue<Integer> queue = new LinkedList<Integer>();
    23         for (int j = 0; j < numCourses; j++) {
    24             if (degree[j] == 0)
    25                 queue.add(j);
    26         }
    27         if (queue.size() == 0)
    28             return new int[0];
    29         int i = 0;
    30         
    31         // begin bfs
    32         while (queue.size() > 0) {
    33             int current = queue.remove();
    34             result[i] = current;
    35             List<Integer> currentList = adjacencyList[current];
    36             for (int j = 1; j < currentList.size(); j++) {
    37                 int tmp = currentList.get(j);
    38                 degree[tmp]--;
    39                 if (degree[tmp] == 0)
    40                     queue.add(tmp);
    41             }
    42             i++;
    43         }
    44         if (i < numCourses)
    45             return new int[0];
    46         return result;
    47     }
    48 }
  • 相关阅读:
    博客园的商业模式
    读书单
    VC++学习笔记
    技术话题
    vc+学习遇到的问题
    常见的Java问题排查方法
    MSDN Library for vs 2010 下载和安装
    WT19i刷机过程
    随记
    WT19i的刷机
  • 原文地址:https://www.cnblogs.com/ireneyanglan/p/4850556.html
Copyright © 2011-2022 走看看