    Upgrade Stages
    For Phase 1 – SAP Upgrade, the enhanced ASAP
    methodology is used. Below are the high-level
    steps to be completed for a successful upgrade.
    Stage 1 – Project Preparation
    • Determine Upgrade Project Organization –structure, roles, people
    • Define Project Procedures –documentation, monitoring, issue resolution
    • Technical Requirements Planning –hardware, software, tools
    • Upgrade Preparation
    • hardware/software requirements
    • detailed technical upgrade plan - minimize down-time
    • contingency
    Stage 2 – Business Blueprint
    • Identify Functionality Enhancements
    • Identify and document new/modified business scenarios
    • Prioritize and select enhancements for
    Phase 1
    • Identify Technical Objects
    • Prepare Technical Objects inventory
    • Identify Usage of Technical Objects
    • Identify strategy for Technical Objects
    • Identify Impact of Upgrade on Technical Objects
    • Identify Archiving parameters
    • Review scope / Prepare firm estimate for subsequent stages
    • Set-up Off-site Development Environment

    Stage 3 – Realization
    • Upgrade and Test Development System (DEV)
    • Perform DEV System Upgrade
    • Perform Upgrade of Technical Objects
    • Archival of data in DEV System
    • Configure new / changed processes
    • Perform Integration Testing in DEV
    • Develop Quality Assurance System (QAS)
    • Install Hardware and Software for QAS
    • Repeat Technical Upgrade Steps
    • Import changes from DEV system
    • Test QAS
    • Set up and Test Connectivity
    Stage 4 – Final Preparation
    • Adapt End User Materials
    • Perform End User Training
    • Put Contingency Plan in Place
    • Take Production System Backup
    Stage 5 – Go Live and Support
    • Transport Production System to Off-site
    • Production system upgrade
    • Repeat technical upgrade steps
    • Import corrections from upgraded QA system
    • Archive application data
    • Post-upgrade support

    Summary of Project Deliverables
    The main deliverables DynPro will produce or contribute to at each stage of the Upgrade process are listed:
    Initial Project Plan
    Project Standards and Procedures
    Technical System Architecture Document
    Project Kick-Off Meeting
    Business Blueprint
    Development System
    Environment Installation
    Business Blueprint Document, including
    Enhancements – Wish List, and scope
    for Phase 1
    Custom Technical Objects Inventory – with
    upgrade strategy
    Requirements for Additional Development
    Archiving Specifications
    Committed implementation Plan and Cost
    Updated Project Plan
    Configuration of SAP and Enhancements
    Development of Agreed Additional
    Development
    Security Set-Up
    Test Plans and Scenarios
    Converted Technical Objects
    Quality System Environment Installation
    Integration Test
    Re-updated Project Plan
    Support Team Documentation
    Support Team Training
    Cut-Over Plans
    Production System Environment Installation
    Upgrade of Production System
    Production Support
    Project Evaluation

  • 相关阅读:
    简单的模板解析函数
    HTML通过事件传递参数到js 二 event
    HTML通过事件传递参数到js一
    通过this获取当前点击选项相关数据
    LeetCode 20. 有效的括号(Valid Parentheses)
    LeetCode 459. 重复的子字符串(Repeated Substring Pattern)
    LeetCode 14. 最长公共前缀(Longest Common Prefix)
    LeetCode 168. Excel表列名称(Excel Sheet Column Title)
    LeetCode 171. Excel表列序号(Excel Sheet Column Number) 22
    LeetCode 665. 非递减数列(Non-decreasing Array)
  • 原文地址:https://www.cnblogs.com/omygod/p/1422733.html
Copyright © 2011-2022 走看看