zoukankan      html  css  js  c++  java
  • SAP Upgrade Strategy 沧海

    Detail information, pls check website: http://sap-abaper.com

    Upgrade Stages
    For Phase 1 – SAP Upgrade, the enhanced ASAP
    methodology is used. Below are the high-level
    steps to be completed for a successful upgrade.
    Stage 1 – Project Preparation
    • Determine Upgrade Project Organization –structure, roles, people
    • Define Project Procedures –documentation, monitoring, issue resolution
    • Technical Requirements Planning –hardware, software, tools
    • Upgrade Preparation
    • hardware/software requirements
    • detailed technical upgrade plan - minimize down-time
    • contingency
    Stage 2 – Business Blueprint
    • Identify Functionality Enhancements
    • Identify and document new/modified business scenarios
    • Prioritize and select enhancements for
    Phase 1
    • Identify Technical Objects
    • Prepare Technical Objects inventory
    • Identify Usage of Technical Objects
    • Identify strategy for Technical Objects
    • Identify Impact of Upgrade on Technical Objects
    • Identify Archiving parameters
    • Review scope / Prepare firm estimate for subsequent stages
    • Set-up Off-site Development Environment

    Stage 3 – Realization
    • Upgrade and Test Development System (DEV)
    • Perform DEV System Upgrade
    • Perform Upgrade of Technical Objects
    • Archival of data in DEV System
    • Configure new / changed processes
    • Perform Integration Testing in DEV
    • Develop Quality Assurance System (QAS)
    • Install Hardware and Software for QAS
    • Repeat Technical Upgrade Steps
    • Import changes from DEV system
    • Test QAS
    • Set up and Test Connectivity
    Stage 4 – Final Preparation
    • Adapt End User Materials
    • Perform End User Training
    • Put Contingency Plan in Place
    • Take Production System Backup
    Stage 5 – Go Live and Support
    • Transport Production System to Off-site
    • Production system upgrade
    • Repeat technical upgrade steps
    • Import corrections from upgraded QA system
    • Archive application data
    • Post-upgrade support

    Summary of Project Deliverables
    The main deliverables DynPro will produce or contribute to at each stage of the Upgrade process are listed:
    Initial Project Plan
    Project Standards and Procedures
    Technical System Architecture Document
    Project Kick-Off Meeting
    Business Blueprint
    Development System
    Environment Installation
    Business Blueprint Document, including
    Enhancements – Wish List, and scope
    for Phase 1
    Custom Technical Objects Inventory – with
    upgrade strategy
    Requirements for Additional Development
    Archiving Specifications
    Committed implementation Plan and Cost
    Updated Project Plan
    Configuration of SAP and Enhancements
    Development of Agreed Additional
    Development
    Security Set-Up
    Test Plans and Scenarios
    Converted Technical Objects
    Quality System Environment Installation
    Integration Test
    Re-updated Project Plan
    Support Team Documentation
    Support Team Training
    Cut-Over Plans
    Production System Environment Installation
    Upgrade of Production System
    Production Support
    Project Evaluation

  • 相关阅读:
    error C4996: Function call with parameters that may be unsafe
    C mysql (C API Commands out of sync; you can't run this command now)
    messagpack的使用
    关于openssl的编译与使用
    openssl & openssh
    解决SOCKET通信 ERROR_INSUFFICIENT_BUFFER错误
    C++ mysql 乱码
    [置顶] docker1.12--docker命令行帮助文档
    [置顶] kubernetes资源类型--secret和Service Account
    [置顶] kubernetes资源类型--Volume
  • 原文地址:https://www.cnblogs.com/omygod/p/1422733.html
Copyright © 2011-2022 走看看