  • Scrum 简介

    Three Roles: Product Owner, Scrum master, Team

    The Product owner: Own and prioritizes the Product Backlog

    1. defines and prioritizes features--owns the gathering of requirements
    2. agrees to iteration ground rules--set length of calendar time for sprint (2,3,4 weeks typical)
    3. does not interfere with sprint(no scope creep)
    4. can pull the plug at any time(has the power)
    5. honors rules and the scrum process during sprints

    Scrum Master: A Boundary Manager, Facilitates the Scrum process, Not a traditional Project manager

    1. supports the team, facilitates the daily scrum meeting.
    2. asks each developer: what do you do yesterday? what are you doing today? what is in your way?
    3. listens and watches carefully during scrum meeting
    4. pays carefull attention to non-verbal cues
    5. removes impediments in way of team
    6. secures resources(monitors, rooms, etc)
    7. communicates to Product Owner

    The team

    1. participates in design to gain understanding of problem/solution space
    2. selects subset of prioritized product backlog for sprint comment: estimates the effort, fills the timebox with work, commits to the work as a team
    3. self organizes: everyone commits to all tasks neccessary during the sprint, determines the nature of self-organization
    4. teams select work for each sprint
    5. teams self-organize
    6. teams have a velocity

    Team velocity: how much work the team can average per iteration, for that team

    1. each time has a personality
    2. each team is unique
    3. teams velocity becomes very predictable over time

    Three ceremonies: Sprint Planning, Daily Scrum, Sprint Review(retrospective)

    ceremony #1: Sprint Planning Meeting

    1. Product Owner reviews: vision, roadmap, release plan
    2. team reviews: estimates for each item on backlog that is a candidate for the sprint
    3. team pulls the work: from the Product Backlog onto the Sprint Backlog

    Ceremony #2: The Daily Scrum

    1. By and for the Team
    2. Other may attend and NOT speack
    3. Team members speack, others listen
    4. Team stays on task with the 3 questions, devergences are addressed offline outside of this meeting
    5. visibility, clear understanding on a day-by-day basis

    Product owners know the score on a daily basis, can pull the plug at any time

    Ceremony #3: Sprint Review Meeting
    Part 01: Product Demo
      Led by Product Owner
    Part 02: Sprint Retrospective
      Led by Scrum Master
      What worked?
      What didn't?
      What adjustments can we make now?

    Three Artifacts: Product Backlog, Sprint Backlog, Burndown Chart

    Artifact #1: Product Backlog

    1. A list of features, prioritized by business value
    2. Each feature has an associated estimate, provided by the ACTUAL team who will do the work
    3. Backlog items come in from deverse sources, including the Team

    Artifact #2: Sprint Backlog

    1. Topmost subset of the Product Backlog, loaded onto the Sprint's "timebox"
    2. usually has more detail attached, including planned hours and primary person responsible to do the work during the Sprint
    3. Is the list of work the Team is addressing during the current Sprint

    Artifact #3: Burndown Chart

    1. Provides visibility into the Sprint
    2. Illustrates progress by the team
    3. Work on the Horizontal, Time on the Vertical

    Three Best Practices: User Stories, Planning Porker, Scrum Board

    Best Practices #1: User Stories

    1. Plan-english requirements, written on common 3*5 index cards
    2. Form: As a type of user, I want to [perform a specific action] such that [result]
    3. Example: "As a web user, I want to make a reservation, such that I may secure my lodging"
    4. Stories that are big are called EPICS
    5. Acceptance criteria goes on card back

    Best Practice #2: Planning Poker

    1. A way for the team to do estimates
    2. Each participant has cards numberd 1,2,3,5,8,13,21
    3. Values represent 'story points' of effort
    4. Players discuss feature, then throw down a card together
    5. Differences are noted and discussed, then process repeats till a concensus estimate is formed

    Best Practice #3: Scrum Board

    1. Scrum Board is a rows-and-columns depictions of work-in-progress
    2. Items of work are rows, work status lables are columns
    3. Work is addressed from top to down
    4. Work migrates from left to right on the board





  • 相关阅读:
    【AS3代码】小游戏打飞机源代码
    【AS3代码】键盘的输入和输出
    PHP多维数组排序
    【AS3代码】一个完整的游戏框架
    【AS3代码】小画板升级版(带重绘回放和清空功能)
    Liunx命令工作总结(1)
    Java NIO基础 我们到底能走多远系列(17)
    ibatis 一对多 解决方案
    图片上传+预览+剪切解决方案我们到底能走多远系列(20)
    Liunx命令工作总结(2)
  • 原文地址:https://www.cnblogs.com/thlzhf/p/3042810.html
Copyright © 2011-2022 走看看