  • hdoj 1050 Moving Tables【贪心区间覆盖】

    Moving Tables

    Time Limit: 2000/1000 MS (Java/Others)    Memory Limit: 65536/32768 K (Java/Others)
    Total Submission(s): 24316    Accepted Submission(s): 8053


    Problem Description
    The famous ACM (Advanced Computer Maker) Company has rented a floor of a building whose shape is in the following figure.



    The floor has 200 rooms each on the north side and south side along the corridor. Recently the Company made a plan to reform its system. The reform includes moving a lot of tables between rooms. Because the corridor is narrow and all the tables are big, only one table can pass through the corridor. Some plan is needed to make the moving efficient. The manager figured out the following plan: Moving a table from a room to another room can be done within 10 minutes. When moving a table from room i to room j, the part of the corridor between the front of room i and the front of room j is used. So, during each 10 minutes, several moving between two rooms not sharing the same part of the corridor will be done simultaneously. To make it clear the manager illustrated the possible cases and impossible cases of simultaneous moving.



    For each room, at most one table will be either moved in or moved out. Now, the manager seeks out a method to minimize the time to move all the tables. Your job is to write a program to solve the manager’s problem.
     
    Input
    The input consists of T test cases. The number of test cases ) (T is given in the first line of the input. Each test case begins with a line containing an integer N , 1<=N<=200 , that represents the number of tables to move. Each of the following N lines contains two positive integers s and t, representing that a table is to move from room number s to room number t (each room number appears at most once in the N lines). From the N+3-rd line, the remaining test cases are listed in the same manner as above.
     
    Output
    The output should contain the minimum time in minutes to complete the moving, one per line.
     
    Sample Input
    3
    4
    10 20
    30 40
    50 60
    70 80
    2
    1 3
    2 200
    3
    10 100
    20 80
    30 50
     
    Sample Output
    10
    20
    30
     
    题解:因为是双排房间,所以对面的两间不可能同时往外搬桌子如1 2处在对面数据
    1  2
    3  4
    结果应该是20,而不是10,
    #include<stdio.h>
    #include<string.h>
    #include<algorithm>
    #define MAX 1100
    using namespace std;
    int dp[MAX];
    bool cmp(int a,int b)
    {
    	return a>b;
    }
    int main()
    {
    	int n,t,m,i,j;
    	scanf("%d",&t);
    	int a,b,c;
    	while(t--)
    	{
    		scanf("%d",&n);
    		memset(dp,0,sizeof(dp));
    		for(i=0;i<n;i++)
    		{
    			scanf("%d%d",&a,&b);
    			if(a>b)
    			{
    				c=a;
    				a=b;
    				b=c;
    			}
    			a=(a+1)/2;
    			b=(b+1)/2;
    			for(j=a;j<=b;j++)
    			{
    				dp[j]++;
    			}
    		}
    		sort(dp,dp+200,cmp);
    		printf("%d
    ",dp[0]*10);
    	}
    	return 0;
    } 
    

      

  • 相关阅读:
    代码动态设置edittext输入类型为密码类型
    java android使用Gson解析泛型json数据
    你必须要懂的APK瘦身知识
    记录一下寄几个儿的greendao数据库升级,可以说是非常菜鸡了嗯
    (通用)Android App代码混淆终极解决方案【转】
    android设置GridView高度自适应,实现全屏铺满效果
    XML解析——Java中XML的四种解析方式
    The SDK platform-tools version ((23)) is too old to check APIs compiled with API 26;
    通过URI返回File文件
    傻瓜式禅道配置
  • 原文地址:https://www.cnblogs.com/tonghao/p/4693428.html
Copyright © 2011-2022 走看看