  • sql跳过非工作日(周末和节假日)

    简介:场景1:基于开始日期和工期,推算结束日期。 场景2:基于开始日期和结束日期,计算工期 注:需要自己做界面维护工作日表(s_WorkDay)和节假日表(s_SpecialDay) 

    涉及到的数据表

    IF OBJECT_ID('s_WorkDay') IS NULL 
    BEGIN 
         CREATE TABLE s_WorkDay([Monday] [TINYINT] 
              ,[Tuesday] [TINYINT] 
              ,[Wednesday] [TINYINT] 
              ,[Thursday] [TINYINT] 
              ,[Friday] [TINYINT] 
              ,[Saturday] [TINYINT] 
              ,[Sunday] [TINYINT] 
         )
    END
    GO
    
    IF OBJECT_ID('s_SpecialDay') IS NULL 
    BEGIN 
         CREATE TABLE s_SpecialDay([SpecialDayGUID] [UNIQUEIDENTIFIER] PRIMARY KEY CLUSTERED NOT NULL  
              ,[BeginDate] [DATETIME] 
              ,[EndDate] [DATETIME] 
              ,[IsWorkDay] [TINYINT] 
              ,[Remarks] [VARCHAR](200) 
         )
    END
    GO

    场景1:根据开始日期和工期,计算结束日期

    --根据开始日期推出结束日期
    
    IF EXISTS ( SELECT  * FROM    dbo.sysobjects WHERE   id = OBJECT_ID(N'[dbo].[fn_GetEndDate]') AND xtype IN ( N'FN', N'IF', N'TF' ) )
    
        DROP FUNCTION [dbo].[fn_GetEndDate]
    
    GO
    
    CREATE   FUNCTION fn_GetEndDate ( @date DATETIME,@Duration INT )
    
    RETURNS DATETIME
    
    AS
    
        BEGIN
    
            DECLARE @Edate DATETIME
    
            DECLARE @IsAdd INT
    
            SET @Edate=@date
    
            SET @Duration=@Duration-1
    
             DECLARE @NoWorkDay TABLE(iDay int)
    
            --非工作日枚举
    
            INSERT INTO @NoWorkDay(iDay) SELECT * FROM dbo.fn_NoWorkDay()
    
           
    
            WHILE ( @Duration > 0 )
    
                BEGIN
    
                    SET @IsAdd=0
    
                    --默认往后+1
    
                    SET @Edate=DATEADD(day, 1, @Edate)
    
                    --如果非工作日,重复循环,否则跳下一步
    
                    IF EXISTS( SELECT TOP 1 1 FROM s_workDay WHERE DATEPART(weekday, @Edate) NOT IN (SELECT * FROM @NoWorkDay))
    
                    BEGIN
    
                     SET @IsAdd=1
    
                     SET @Duration = @Duration - 1
    
                    END
    
                    --如果当前日期在特殊非工作日中,则不跳
    
                    IF EXISTS( SELECT TOP 1 1 FROM s_SpecialDay WHERE (@Edate BETWEEN begindate AND enddate) AND IsWorkDay=0 AND @IsAdd=1)
    
                    BEGIN
    
                      SET @Duration = @Duration + 1
    
                    END
    
                    --如果当前日期在特殊工作日中,则跳1
    
                      IF EXISTS( SELECT TOP 1 1 FROM s_SpecialDay WHERE (@Edate BETWEEN begindate and enddate) AND IsWorkDay=1 AND @IsAdd=0)
    
                    BEGIN
    
                      SET @Duration = @Duration -1
    
                    END
    
                END
    
            RETURN @Edate
    
        END
    
    GO

    场景2:根据两个日期,计算工期

    --计算工期
    
    IF EXISTS ( SELECT  * FROM    dbo.sysobjects WHERE   id = OBJECT_ID(N'[dbo].[fn_GetDuration]') AND xtype IN ( N'FN', N'IF', N'TF' ) )
    
        DROP FUNCTION [dbo].[fn_GetDuration]
    
    GO
    
    CREATE   FUNCTION fn_GetDuration(@BeginDate DATETIME,@EndDate DATETIME)
    
    RETURNS INT
    
    AS
    
        BEGIN
    
            DECLARE @iCount INT
    
            --A:取出常规工作日
    
            SELECT  @iCount = ISNULL(dbo.fn_GetWorkDay(@BeginDate, @EndDate), 0) 
    
           
    
            --B:减去特殊非工作日
    
            SELECT  @iCount = @iCount
    
                    - ISNULL(SUM(dbo.fn_GetWorkDay(CASE WHEN begindate < @BeginDate
    
                                                        THEN @BeginDate
    
                                                        ELSE begindate
    
                                                   END,
    
                                                   CASE WHEN enddate > @EndDate
    
                                                        THEN @EndDate
    
                                                        ELSE enddate
    
                                                   END)), 0)
    
            FROM    s_SpecialDay
    
            WHERE   isworkday = 0
    
                    AND SpecialDayGUID NOT IN (
    
                    SELECT  SpecialDayGUID
    
                    FROM    s_SpecialDay
    
                    WHERE   ( begindate > @EndDate
    
                              AND enddate > @EndDate
    
                            )
    
                            OR ( begindate < @BeginDate
    
                                 AND enddate < @BeginDate
    
                               ) )
    
         
    
            ----C:加上特殊工作日
    
            SELECT  @iCount = @iCount + ISNULL(SUM(DATEDIFF(dd,
    
                                                            CASE WHEN begindate < @BeginDate
    
                                                                 THEN @BeginDate
    
                                                                 ELSE begindate
    
                                                            END,
    
                                                            CASE WHEN enddate > @EndDate
    
                                                                 THEN @EndDate
    
                                                                 ELSE enddate
    
                                                            END)
    
                                                   - dbo.fn_GetWorkDay(CASE
    
                                                                  WHEN begindate < @BeginDate
    
                                                                  THEN @BeginDate
    
                                                                  ELSE begindate
    
                                                                  END,
    
                                                                  CASE
    
                                                                  WHEN enddate > @EndDate
    
                                                                  THEN @EndDate
    
                                                                  ELSE enddate
    
                                                                  END)), 0)
    
            FROM    s_SpecialDay
    
            WHERE   isworkday = 1
    
                    AND SpecialDayGUID NOT IN (
    
                    SELECT  SpecialDayGUID
    
                    FROM    s_SpecialDay
    
                    WHERE   ( begindate > @EndDate
    
                              AND enddate > @EndDate
    
                            )
    
                            OR ( begindate < @BeginDate
    
                                 AND enddate < @BeginDate
    
                               ) )
    
            RETURN @iCount
    
        END
    
    GO

    需要用到的函数

    IF EXISTS ( SELECT  *
    
                FROM    dbo.sysobjects
    
                WHERE   id = OBJECT_ID(N'[dbo].[fn_NoWorkDay]')
    
                        AND xtype IN ( N'FN', N'IF', N'TF' ) )
    
        DROP FUNCTION [dbo].[fn_NoWorkDay]
    
    GO
    
    --输出非工作日
    
    CREATE   FUNCTION fn_NoWorkDay()
    
    RETURNS @NoWorkDay TABLE ( iDay INT )
    
    AS
    
        BEGIN
    
            INSERT  INTO @NoWorkDay
    
                    ( iDay
    
                    )
    
                    SELECT  2
    
                    FROM    s_WorkDay
    
                    WHERE   Monday = 0
    
            INSERT  INTO @NoWorkDay
    
                    ( iDay
    
                    )
    
                    SELECT  3
    
                    FROM    s_WorkDay
    
                    WHERE   Tuesday = 0
    
            INSERT  INTO @NoWorkDay
    
                    ( iDay
    
                    )
    
                    SELECT  4
    
                    FROM    s_WorkDay
    
                    WHERE   Wednesday = 0
    
            INSERT  INTO @NoWorkDay
    
                    ( iDay
    
                    )
    
                    SELECT  5
    
                    FROM    s_WorkDay
    
                    WHERE   Thursday = 0
    
            INSERT  INTO @NoWorkDay
    
                    ( iDay
    
                    )
    
                    SELECT  6
    
                    FROM    s_WorkDay
    
                    WHERE   Friday = 0
    
            INSERT  INTO @NoWorkDay
    
                    ( iDay
    
                    )
    
                    SELECT  7
    
                    FROM    s_WorkDay
    
                    WHERE   Saturday = 0
    
            INSERT  INTO @NoWorkDay
    
                    ( iDay
    
                    )
    
                    SELECT  1
    
                    FROM    s_WorkDay
    
                    WHERE   Sunday = 0
    
            RETURN 
    
        END        
    
     
    
    Go
    
    --计算工作日
    
    IF EXISTS ( SELECT  *
    
                FROM    dbo.sysobjects
    
                WHERE   id = OBJECT_ID(N'[dbo].[fn_GetWorkDay]')
    
                        AND xtype IN ( N'FN', N'IF', N'TF' ) )
    
        DROP FUNCTION [dbo].[fn_GetWorkDay]
    
    GO
    
    CREATE   FUNCTION fn_GetWorkDay(@BeginDate DATETIME,@EndDate DATETIME)
    
    RETURNS INT
    
    AS
    
        BEGIN
    
            DECLARE @NoWorkDay TABLE(iDay int)
    
            --非工作日枚举
    
            INSERT INTO @NoWorkDay(iDay) SELECT * FROM fn_NoWorkDay()
    
            DECLARE @i INT,@iCount INT
    
            SET @iCount=0
    
            SET @i = DATEDIFF(day, @BeginDate, @EndDate) 
    
            WHILE ( @i >= 0 )
    
                BEGIN
    
                    --如果开始日期往后顺延,遇到非工作日,则不计数
    
                    IF EXISTS( SELECT TOP 1 1 FROM s_workDay WHERE DATEPART(weekday, @BeginDate) NOT IN (SELECT * FROM @NoWorkDay))
    
                    BEGIN
    
                     SET @iCount=@iCount+1
    
                    END
    
                    SET @BeginDate=DATEADD(day, 1, @BeginDate)
    
                    SET @i = @i - 1 
    
                END
    
            RETURN @iCount
    
        END
    
    go
  • 相关阅读:
    Spring Boot实战二:集成Mybatis
    Spring Boot实战一:搭建Spring Boot开发环境
    Oracle 11g安装和PL/SQL连接完全解读(连接本地数据库)
    Spring事务详解
    RabbitMQ学习笔记六:RabbitMQ之消息确认
    RabbitMQ学习笔记五:RabbitMQ之优先级消息队列
    RabbitMQ学习笔记四:RabbitMQ命令(附疑难问题解决)
    RabbitMQ学习笔记三:Java实现RabbitMQ之与Spring集成
    RabbitMQ学习笔记二:Java实现RabbitMQ
    Spark 读 Hive(不在一个 yarn 集群)
  • 原文地址:https://www.cnblogs.com/KingUp/p/5722537.html
Copyright © 2011-2022 走看看