    137.Your company wants to upgrade the current production database to the RAC environment. To

    perform testing before migrating to the RAC environment, you performed the workload capture on the

    production database to record the peak workload. You set up the test RAC database and want to replay

    the recorded workload on the testmachine. Note the following steps that you may require to replay the

    database workload:

    1) Preprocess the captured workload.

    2) Restart the database in RESTRICTED mode.

    3) Set up the Replay Clients.

    4) Restore the test database to the point when the capture started.

    5) Remap connections.

    Arrange the steps required in the correct sequence to accomplish this task on the test machine.

    A. 1, 4, 5, 3 (2 is not required.)

    B. 1, 4, 3, 5 (2 is not required.)

    C. 1, 2, 4, 5 (3 is not required.)

    D. 2, 1, 5, 3, 4

    E. 1, 2, 4, 5, 3

    Answer: A

    答案解析:

    参考:http://blog.csdn.net/rlhua/article/details/14053709

    步骤为:预处理工作量--然后重放工作量,重放工作量先决条件之一为还原数据库--定制选项中的连接映射--设置重放客户机,开始重放工作量。


  • 相关阅读:
    2018年4月22日笔记
    2018年4月19日笔记
    2018年4月17日笔记
    2018年4月14日笔记
    2018年4月12日笔记
    课堂练习找水王
    评价软件
    第十一周进度条
    典型用户场景、用户场景描述
    构建之法阅读笔记04
  • 原文地址:https://www.cnblogs.com/hzcya1995/p/13316611.html
Copyright © 2011-2022 走看看